Who can help to translate the following requirements which is from AMS 2750E?

Thanks very much.

3.5.18 Relocation of Hot or Cold Recording Sensors for Class A or C Instrumentation
When the hottest and coldest temperature locations change within the furnace (based on the final readings from the most
recent Temperature Uniformity Survey), the recording sensor locations for types A and C instrumentation may need to be
moved within the furnace to reflect the new hottest and coldest locations within the work zone. These sensors do not
require relocation if the overall temperature uniformity does not exceed one half of the maximum temperature uniformity
tolerance for the applicable furnace class at all temperatures surveyed, or if the difference between the measured
temperature at the current recording locations and the actual respective hottest and coldest measured areas is less than
the system accuracy test (SAT) tolerance for the applicable furnace class.

签到天数: 34 天

[LV.5]常住居民I

发表于 2020-1-17 15:36:43 | 显示全部楼层
3.5.18重新安置用于A类或C类仪表的热或冷记录传感器
当炉内最高温和最低温的位置发生变化时(根据最低温的最终读数)
最近的温度均匀性调查),A型和C型仪器的记录传感器位置可能需要
在炉内移动,以反映新的最热和最冷的位置在工作区内。这些传感器不会
如果整体温度均匀性不超过最高温度均匀性的一半,则需要重新定位
适用炉类在所有调查温度下的公差,或测量值之间的差异
温度在当前记录的位置和实际分别测得的最热和最冷的区域小于
适用炉类的系统精度测试(SAT)公差。

评分

参与人数 1热处理币 +40 收起 理由
cjzhou + 40 感谢参与!

查看全部评分

回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

苏州工业园区热海热处理设备有限公司 热处理论坛合作伙伴广告位 苏州出兴自动化设备有限公司

QQ|Archiver|手机版|小黑屋|热处理论坛 ( 苏ICP备11036679号 公安机关备案号:32059002001695 )

GMT+8, 2020-4-5 14:44 , Processed in 0.040923 second(s), 21 queries .

Powered by Discuz! X3.4

Copyright © 2001-2020, Tencent Cloud.

快速回复 返回顶部 返回列表